Solar permits and utility approval in St. George, explained
· 1 min read
Most of the time on a solar project isn't spent on the roof. It's spent on paperwork. Here's what that looks like in Southern Utah, so the timeline makes sense.
The typical timeline
From signed agreement to a working system, most projects take about 6 to 10 weeks. The install itself is often a day or two. The rest is design, permits, inspection and utility approval.
1. Site evaluation and design
Someone checks the roof, the electrical panel and shading, then finalizes the design. The panel layout and electrical plans are what the city reviews.
2. Building permit
The plans go to your city or county building department. St. George, Washington, Hurricane, Ivins, Santa Clara and Cedar City each run their own review. Turnaround varies with how busy they are.
3. Utility interconnection application
Your utility has to approve connecting the system to the grid. In Southern Utah that might be Rocky Mountain Power, or a city-owned utility such as St. George Energy Services. Each has its own application and rules for exported solar.
4. Installation
Once the permit is approved, the install is scheduled. A good crew leaves clean conduit runs, clear labeling and a tidy site.
5. Inspection
The city inspects the finished work. If anything needs correcting, it's fixed and re-inspected.
6. Permission to operate (PTO)
After inspection, the utility gives the final OK and may swap or reprogram your meter. Only then should the system be turned on for good.
What you should hear along the way
You shouldn't have to chase anyone for updates. At each milestone, from permit submitted to PTO, you should get a short note on where things stand and what's next.
That's how Fortius runs every project, with one point of contact the whole way. See the areas we serve or ask a question below.